PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI ENCLAVE

by SAIRAJDEVELOP

S NO 13 HNO 1, MACCHA PADA, 401107

Dec 2026
Possession
36.4%
Built
0
Complaints
108
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 36.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700012717
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
36.4% complete
Units sold
96 of 108

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains10%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Floors
11
Unit mix
96 res ยท 12 comm
Architect
B A C PLANNERS AND ENGINEERS PVT LTD

Buyer community

Connect with other buyers and owners of SAI ENCLAVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI ENCLAVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.