PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ONE PARK AVENUE - AVENUE 1

by Purva Oak Private Limited

S NO 114/4 115/2, Thane, 400607

Dec 2026
Possession
27.7%
Built
21
Complaints
252
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • 21 RERA complaints. 21 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 27.7%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700013016
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
27.7% complete
Units sold
88 of 252

RERA complaint record21 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Floors
42
Unit mix
252 res ยท 0 comm
Architect
Saakaar

Buyer community

Connect with other buyers and owners of ONE PARK AVENUE - AVENUE 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ONE PARK AVENUE - AVENUE 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.