Under construction

PALAVA AURELIA - C, H, I

by Palava Dwellers Private Limited

144/8, 42/1, 144/7, 42/8, 44/3/1 all pt, Palava, 421202

Jun 2023
Possession
54.5%
Built
2
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 54.5%.
  • Promised amenities not started. Sports / Jogging is at 0% build with possession due Jun 2023 per the RERA filing.

Official RERA facts

Registration
P51700013073
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
54.5% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
Templenot started
Sports Complexnot started
Clubhousenot started
Closed Parkingsdone

Building & registration

RERA registered
Sept 2017
Floors
17

Buyer community

Connect with other buyers and owners of PALAVA AURELIA - C, H, I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALAVA AURELIA - C, H, I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.