- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Dec 2026 but construction is only at 28.2%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
A full city of its own โ lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51700013100
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2023
- Construction
- 28.2% complete
- Units sold
- 74 of 149
RERA complaint record6 records
- ComplaintCC00600000019650927 Mar 2021Varun Vijay Sharma & Ms. Mandeepkaur R Mundra vs M/s. Man Realty Limited196509.pdf on MahaRERA
- ComplaintCC00600000019530719 Dec 2020Adil Qureshi vs Man Realty Ltd.43_Order_195307 signed.pdf on MahaRERA
- ComplaintCC00600000019460831 Oct 2020RAVI KUMAR NAGARAJAN vs MAN REALTY LTDFinal Order 194608.pdf on MahaRERA
- ComplaintCC00600000002309019 Mar 2018ketan patil vs MAN REALTY LTDCC006_23090.pdf on MahaRERA
- Misc. applicationCC00600000002309019 Mar 2018ketan patil vs MAN REALTY LTDCC006_23090.pdf on MahaRERA
- ComplaintCC00600000002299827 Jan 2018Ratish Nair vs Man Realty Limited22998 Ratish Nair Vs Man Realty Ltd.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Sept 2017
- Floors
- 42
- Unit mix
- 149 res ยท 0 comm
- Architect
- Saakaar
Buyer community
Connect with other buyers and owners of ONE PARK AVENUE - AVENUE 6 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ONE PARK AVENUE - AVENUE 6. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.