Under construction

TALL RESIDENCY

by TALL CONSTRUCTIONS

9/9 8, TEMGHAR, 421302

Dec 2028
Possession
30.6%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Jun 2021, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51700013609
Status
New
Stage
Certificate Signed
Possession
December 2028originally June 2021
Construction
30.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2017
Floors
14

Buyer community

Connect with other buyers and owners of TALL RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TALL RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.