PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Yug Heights

by M/s R. S. Constructions

Survey No 19 Hissa No5 Village Sangarli Taluka Thane, Thane, 421204

High risk
  • Recovery warrants issued. MahaRERA has issued 15 recovery warrants against this project โ€” the strongest enforcement action on record.
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • 75 RERA complaints. 75 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700014553
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
62.5% complete
Units sold
0 of 0

RERA complaint record75 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2017
Floors
19

Buyer community

Connect with other buyers and owners of Yug Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Yug Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.