๐Ÿ—๏ธ
Under construction

Enrich Eva

by DEVDAS TUKARAM CHAUGHULE

218.2192111,2112,2113, Nadgaon, 421601

Dec 2026
Possession
37.3%
Built
5
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 37.3%.

Official RERA facts

Registration
P51700014605
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
37.3% complete
Units sold
0 of 0

RERA complaint record5 records

  • ComplaintCC1260050629 Jan 2026
    Sangharakshit Ramji Kadam vs Enrich Housing
  • ComplaintCC1260049327 Jan 2026
    Princy Swapnil Hule vs DEVDAS TUKARAM CHAUGHULE
  • ComplaintCC1260046125 Jan 2026
    Rahul Prahlad Sharma vs DEVDAS TUKARAM CHAUGHULE
  • ComplaintCC1260044324 Jan 2026
    Darshana Deepak Sarwankar vs DEVDAS TUKARAM CHAUGHULE
  • ComplaintCC126000916 Jan 2026
    Edwin Juje Fernandes vs DEVDAS TUKARAM CHAUGHULE

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2017
Floors
5

Buyer community

Connect with other buyers and owners of Enrich Eva โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Enrich Eva. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.