Dec 2026
Possession
60.6%
Built
0
Complaints
200
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700014766
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2023
- Construction
- 60.6% complete
- Units sold
- 96 of 200
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths60%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains60%
Landscaping & Tree Planting30%
Street Lighting20%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Jan 2018
- Floors
- 38
- Unit mix
- 184 res ยท 16 comm
- Architect
- k.k and associates
Buyer community
Connect with other buyers and owners of SINI ENTERPRISES โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SINI ENTERPRISES. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.