Under construction
ARIHANT AAROHI PHASE II
by ARIHANT SUPERSTRUCTURES LIMITED
15/2, VILLAGE PADLE, 421204
Dec 2024
Possession
90.5%
Built
5
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.5%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.
Official RERA facts
- Registration
- P51700015328
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 90.5% complete
- Units sold
- 0 of 0
RERA complaint record5 records
- ComplaintCC1250335520 Sept 2025Sujata Peter Kittan vs ARIHANT SUPERSTRUCTURES LIMITEDCommon Order of Arihant Superstructures Limited-2 complaints.pdf on MahaRERA
- ComplaintCC1250103827 Mar 2025Ganesh Chavan vs ARIHANT SUPERSTRUCTURES LIMITEDCommon Order of Arihant Suprestriucture - 2 complaints.pdf on MahaRERA
- Misc. applicationCC1250096519 Mar 2025Priya Dsouza vs ARIHANT SUPERSTRUCTURES LIMITED
- ComplaintCC1250096519 Mar 2025Priya Dsouza vs ARIHANT SUPERSTRUCTURES LIMITEDCommon Order of Arihant Superstructures Limited-2 complaints.pdf on MahaRERA
- ComplaintCC1250084111 Mar 2025Chetan Sudam Madhavi vs ARIHANT SUPERSTRUCTURES LIMITEDCommon Order of Arihant Suprestriucture - 2 complaints.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water60%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting10%
Energy managemcnt20%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Feb 2018
- Floors
- 19
Buyer community
Connect with other buyers and owners of ARIHANT AAROHI PHASE II โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ARIHANT AAROHI PHASE II. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.