Sara Heights
G No 47, Hissa No. 19 and 20, At Manjarli Badlapur, 421503
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 45.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
The value frontier beyond Kalyan โ low-rise affordability, improving rail links.
- Growth drivers:
- Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
- Who buys here:
- First-home buyers stretching every rupee.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51700015758
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 45.2% complete
- Units sold
- 25 of 115
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2018
- Floors
- 9
- Unit mix
- 106 res ยท 9 comm
Buyer community
Connect with other buyers and owners of Sara Heights โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Sara Heights. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.