High risk
- Possession delayed ~6 yrs. Originally promised Oct 2024, now proposed Dec 2030 per the RERA filing.
- 15 RERA complaints. 15 complaint records are disclosed against this project on MahaRERA.
Navi Mumbai (Vashi–Nerul)Mid-income
Planned-city order — wide roads, node markets, established social infra.
- Growth drivers:
- Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
- Who buys here:
- Professionals wanting planned-city living with airport-corridor upside.
PropPin area guide — editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51700016164
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030originally October 2024
- Construction
- 63.6% complete
- Units sold
- 44 of 70
RERA complaint record15 records
- ComplaintCC126012699 Mar 2026NIVASTI DEVELOPERS LLP vs Sagar Kale
- ComplaintCC1250459023 Dec 2025Om Khemraj Gahlot vs NIVASTI DEVELOPERS LLPWithdrawal order CC12504590 S.pdf on MahaRERA
- ComplaintCC125038231 Nov 2025Rajesh Viswanathan vs NIVASTI DEVELOPERS LLPOrder 16.pdf on MahaRERA
- ComplaintCC1250381731 Oct 2025Sagar Kale vs NIVASTI DEVELOPERS LLP14 - Order.pdf on MahaRERA
- ComplaintCC1250365514 Oct 2025NIVASTI DEVELOPERS LLP vs Aditya Rajesh Daga34- disposed off order withdrawal order signed.pdf on MahaRERA
- ComplaintCC1250365714 Oct 2025NIVASTI DEVELOPERS LLP vs Kamlesh Dadlani10 withdrawal.pdf on MahaRERA
- ComplaintCC1250365614 Oct 2025NIVASTI DEVELOPERS LLP vs Gaurav Ajay Saraf50 withdrawal signed.pdf on MahaRERA
- ComplaintCC1250365414 Oct 2025NIVASTI DEVELOPERS LLP vs Bhawarlal Bisanlal KhatriOrder 14.pdf on MahaRERA
- ComplaintCC1250290218 Aug 2025Rajesh Kumar Daga vs NIVASTI DEVELOPERS LLP
- ComplaintCC1250196616 Jun 2025Rakesh Bhawarlala khatri vs NIVASTI DEVELOPERS LLPWithdrawal srno30 signed.pdf on MahaRERA
- ComplaintCC1250144329 Apr 2025Ashok Dayaramani vs NIVASTI DEVELOPERS LLPserial 30 withdrawal order SIGNED.pdf on MahaRERA
- ComplaintCC1250144029 Apr 2025Ashok Dayaramani vs NIVASTI DEVELOPERS LLPserial 29 withdrawal order SIGNED.pdf on MahaRERA
- ComplaintCC125004087 Feb 2025Kamlesh Dadlani vs NIVASTI DEVELOPERS LLP12500408-9 withdrawal.pdf on MahaRERA
- ComplaintCC1240112113 Dec 2024Gaurav Ajay Saraf vs NIVASTI DEVELOPERS LLPWithdrawal srno28 signed.pdf on MahaRERA
- ComplaintCC1240109711 Dec 2024Aditya Daga vs NIVASTI DEVELOPERS LLPWithdrawal srno27 signed.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Apr 2018
- Floors
- 39
- Unit mix
- 48 res · 22 comm
- Architect
- RAJESH RADHAKISHAN CHANDA
Buyer community
Connect with other buyers and owners of AVISAA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching AVISAA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities — what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.