Under construction

SURVEY NO 162 VILLAGE KHONI TAL KALYAN

by MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY

162, AT POST KHONI, 421301

Jan 2028
Possession
87.6%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jan 2022, now proposed Jan 2028 per the RERA filing.

Official RERA facts

Registration
P51700016831
Status
New
Stage
Certificate Signed
Possession
January 2028originally January 2022
Construction
87.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths55%
Water Supply55%
Sewerage (Chamber, Lines, Septic Tank , STP)55%
Storm Water Drains55%
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jun 2018
Floors
16
Architect
Anil Rooplal Sharma

Buyer community

Connect with other buyers and owners of SURVEY NO 162 VILLAGE KHONI TAL KALYAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SURVEY NO 162 VILLAGE KHONI TAL KALYAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.