PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SIDDHESHWAR

by SIDDHESHWAR GROUP

SURVEY NO 52, HISSA NO 2P CITY SURVEY NO 3798 TO 3808 AND 3812 TO 3816 AYRE GAON DOMBIVLI EAST, DOMBIVLI EAST, 421201

Dec 2023
Possession
52.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 52.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P51700016871
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
52.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2018
Floors
8

Buyer community

Connect with other buyers and owners of SIDDHESHWAR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SIDDHESHWAR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.