Panvelkar Aangan Phase 1
Survey No 46/7 P, 46/11B, 49/1 plus 3P, Vashind, 421604
Dec 2027
Possession
48.5%
Built
0
Complaints
345
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700017019
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2023
- Construction
- 48.5% complete
- Units sold
- 140 of 345
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jul 2018
- Floors
- 8
- Unit mix
- 318 res ยท 27 comm
- Architect
- The Design India
Buyer community
Connect with other buyers and owners of Panvelkar Aangan Phase 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Panvelkar Aangan Phase 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance