All RERA projects
๐๏ธ
Under construction
Suraj Co.Op.HSG.SOC.Ltd
S No /Gut No 48/3 Plot No 6 To 10, Sarvodaya Nagar, 421503
May 2024
Possession
27.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (May 2024) has passed with construction at 27.5%.
Official RERA facts
- Registration
- P51700017984
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2024
- Construction
- 27.5% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Oct 2018
- Floors
- 5
Buyer community
Connect with other buyers and owners of Suraj Co.Op.HSG.SOC.Ltd โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Suraj Co.Op.HSG.SOC.Ltd. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.