GOVARDHANI DARSHAN

by BHARATI CONSTRUCTION CO

CTS 117A B, Thane, 400614

High risk
  • Possession delayed ~3 yrs. Originally promised Nov 2024, now proposed Oct 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700018294
Status
New
Stage
Certificate Signed
Possession
October 2027originally November 2024
Construction
0% complete
Units sold
0 of 30

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Oct 2018
Floors
10
Unit mix
30 res · 0 comm
Architect
DEEPALI KULKARNI CHAWAK

Buyer community

Connect with other buyers and owners of GOVARDHANI DARSHAN — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching GOVARDHANI DARSHAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.