Sai Suman Tower
by M/S. RBG Constructions & Developers Pvt. Ltd.
S.No.13, H.No.1/1, 1/3, 1/4 AND 2, Village Tisgaon, 421306
- Possession delayed ~2 yrs. Originally promised May 2022, now proposed Sept 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P51700018433
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2024originally May 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Nov 2018
- Floors
- 18
Buyer community
Connect with other buyers and owners of Sai Suman Tower โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Sai Suman Tower. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.