- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 81.8%.
Official RERA facts
- Registration
- P51700018463
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2022
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC1260212711 Apr 2026Abhimanyu Behera vs GOODWILL CONSTRUCTIONS
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths45%
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains30%
Landscaping & Tree Planting50%
Street Lightingnot started
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal80%
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station70%
Building & registration
- RERA registered
- Nov 2018
- Floors
- 25
Buyer community
Connect with other buyers and owners of GOODWILL UNITY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching GOODWILL UNITY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.