Under construction

Uma Ashish A Wing

by Uma Housing

S No 5 Hiss No 19A, Badlapur (E), 421503

Dec 2019
Possession
27.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2019 per the RERA filing.

Official RERA facts

Registration
P51700018549
Status
New
Stage
Certificate Signed
Possession
December 2019
Construction
27.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2018
Floors
5

Buyer community

Connect with other buyers and owners of Uma Ashish A Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Uma Ashish A Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.