Rai s Heaven

by RAI RESIDENCY Private Limited

Survey no 44 Hissa no 11 and 12 Survey no 53 Hissa no 1 and 4 and Survey no 54 Hissa no 2, Kalyan, 421306

High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 44.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700018559
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
44.8% complete
Units sold
122 of 249

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2018
Floors
19
Unit mix
223 res · 26 comm

Buyer community

Connect with other buyers and owners of Rai s Heaven — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Rai s Heaven. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.