SUDARSHAN GARDEN PHASE II

by Sudarshan Nirman Co

SURVEY NO 34 1A1, Next to Milletary School Campus, 421605

Dec 2026
Possession
47.7%
Built
0
Complaints
60
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 47.7%.

Official RERA facts

Registration
P51700018847
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
47.7% complete
Units sold
31 of 60

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths5%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Dec 2018
Floors
5
Unit mix
60 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SUDARSHAN GARDEN PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SUDARSHAN GARDEN PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.