Under construction

ANANTA

by VIRTUOSO REALTY ENTERPRISES

56, MIRA ROAD, 401107

Dec 2026
Possession
60.3%
Built
1
Complaints
232
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jan 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700019629
Status
New
Stage
Certificate Signed
Possession
December 2026originally January 2025
Construction
60.3% complete
Units sold
109 of 232

RERA complaint record1 record

  • ComplaintCC1260396926 Jun 2026
    Madhavi Suresh Patil vs VIRTUOSO REALTY ENTERPRISES

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Feb 2019
Floors
24
Unit mix
196 res ยท 36 comm
Architect
RAJENDRA B AHIR

Buyer community

Connect with other buyers and owners of ANANTA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANANTA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.