All RERA projects
๐๏ธ
Under construction
RAGHU NANDAN SANKUL
by JAI MATA DI BUILDERS & DEVELOPERS
191/2/1 , 191/1, NEAR MARUTI MANDIR, 421601
Dec 2026
Possession
48.9%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 48.9%.
Official RERA facts
- Registration
- P51700019656
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2023
- Construction
- 48.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting50%
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Feb 2019
- Floors
- 6
Buyer community
Connect with other buyers and owners of RAGHU NANDAN SANKUL โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RAGHU NANDAN SANKUL. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.