PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHIV PRIYA APARTMENT

by SHREENEEL BUILDER

28/2/C, KATRAP, 421503

Dec 2025
Possession
54.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 54.5%.

Official RERA facts

Registration
P51700019714
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
54.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Energy managemcntnot started

Building & registration

RERA registered
Feb 2019
Floors
5

Buyer community

Connect with other buyers and owners of SHIV PRIYA APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIV PRIYA APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.