Under construction

Lodha Amara Tower 44

by LODHA DEVELOPERS LIMITED

66/0, 68/1, 68/2, 70/1, Kolshet, 400607

Jun 2028
Possession
47.9%
Built
0
Complaints
154
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Sept 2025, now proposed Jun 2028 per the RERA filing.

Official RERA facts

Registration
P51700020123
Status
New
Stage
Certificate Signed
Possession
June 2028originally September 2025
Construction
47.9% complete
Units sold
41 of 154

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply68%
Sewerage (Chamber, Lines, Septic Tank , STP)74%
Storm Water Drains70%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings70%
Treatment And Disposal Of Sewage And Sullage Water84%
Solid Waste Management And Disposal84%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
35
Unit mix
154 res ยท 0 comm
Architect
Pradeep Kamble

Buyer community

Connect with other buyers and owners of Lodha Amara Tower 44 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Lodha Amara Tower 44. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.