Under construction

PALAVA SERENITY D

by Lodha Developers Limited

64/1 pt and 148/15 pt, PALAVA, 421204

Apr 2024
Possession
81.8%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Apr 2024) has passed with construction at 81.8%.

Official RERA facts

Registration
P51700020124
Status
New
Stage
Certificate Signed
Possession
April 2024
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parking95%
Closing Parkingdone

Building & registration

RERA registered
Mar 2019
Floors
21

Buyer community

Connect with other buyers and owners of PALAVA SERENITY D โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALAVA SERENITY D. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.