All RERA projects
๐๏ธ
Under construction
Lodha Amara Tower 24 and 25
72/5, 72/7, 72/8 ,72/9 ,73/3,73/4,73/7, BALKUM Thane West, 400607
Mar 2028
Possession
81.8%
Built
0
Complaints
460
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2024, now proposed Mar 2028 per the RERA filing.
Official RERA facts
- Registration
- P51700020128
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2028originally June 2024
- Construction
- 81.8% complete
- Units sold
- 445 of 460
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2019
- Floors
- 40
- Unit mix
- 460 res ยท 0 comm
- Architect
- Pradeep Kamble
Buyer community
Connect with other buyers and owners of Lodha Amara Tower 24 and 25 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Lodha Amara Tower 24 and 25. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance