Lodha Amara Tower 49 and 50

by LODHA DEVELOPERS LIMITED

65/1 AT VILLAGE BALKUM and 51/3 AT VILLAGE KOLSHET, KOLSHET, 400607

Dec 2028
Possession
73.9%
Built
3
Complaints
350
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2025, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51700020157
Status
New
Stage
Certificate Signed
Possession
December 2028originally September 2025
Construction
73.9% complete
Units sold
305 of 350

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting50%
Street Lighting50%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station82%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
39
Unit mix
350 res ยท 0 comm
Architect
Pradeep Kamble

Buyer community

Connect with other buyers and owners of Lodha Amara Tower 49 and 50 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Lodha Amara Tower 49 and 50. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.