Lodha Amara -Tower 42 and 43
64/3,65/1,65/2,66/0,70/1, BALKUM Thane West, 400607
Dec 2027
Possession
65%
Built
3
Complaints
462
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2025, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700020164
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally March 2025
- Construction
- 65% complete
- Units sold
- 308 of 462
RERA complaint record3 records
- ComplaintCC00600000042883514 Jan 2024Binal Bhavesh Kanani vs Lodha (Macrotech Developers) Ltd.Withdrwal order 428835.pdf on MahaRERA
- ComplaintCC00600000036460016 Mar 2023MIlind K Mahure vs Macrotech Devlopers LtdLOP ORDER 364600.pdf on MahaRERA
- ComplaintCC0060000001980932 Sept 2021SEEMA MOURYA vs MACROTECH DEVELOPERS LIMITEDScan order CC006-198093 Dated 19-05-2022.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supply68%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting80%
Energy managemcnt70%
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Space10%
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2019
- Floors
- 39
- Unit mix
- 462 res ยท 0 comm
- Architect
- Pradeep Kamble
Buyer community
Connect with other buyers and owners of Lodha Amara -Tower 42 and 43 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Lodha Amara -Tower 42 and 43. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.