Under construction

Sector 5 - Wing C

by Agile Real Estate Pvt. Ltd.

New S No 89/1 Part 89/2/B Part 89/3 Part 89/4 Part 89/5 Part of Village Balkum, Village Balkum, Thane, 400607

Dec 2027
Possession
51.2%
Built
0
Complaints
233
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700020196
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
51.2% complete
Units sold
173 of 233

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Mar 2019
Floors
51
Unit mix
233 res ยท 0 comm
Architect
Jethe & Associates

Buyer community

Connect with other buyers and owners of Sector 5 - Wing C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sector 5 - Wing C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.