Tokyo Bay Phase - 2C
by Puranik Tokyo Bay Private Limited
21/11 A Part and 20/1 Part, Near Aarambh Project, 400615
Feb 2027
Possession
0%
Built
2
Complaints
0
Units
High risk
- Behind schedule. Possession is due Feb 2027 but construction is only at 0%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700020265
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2027
- Construction
- 0% complete
- Units sold
- 0 of 0
RERA complaint record2 records
- ComplaintCC1260164423 Mar 2026Leena Perinbadass Daniel vs Puranik Tokyo Bay Private LimitedFinal Order of Leena Daniel - Wrong Project Number.pdf on MahaRERA
- ComplaintCC00600000009009212 Jul 2019UNNATHI ASSOCIATES vs M/s. Sai Pushp EnterprisesUnnathi Associates-02032020112056.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Mar 2019
- Floors
- 5
Buyer community
Connect with other buyers and owners of Tokyo Bay Phase - 2C โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Tokyo Bay Phase - 2C. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.