Mar 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2023 per the RERA filing.
Official RERA facts
- Registration
- P51700020354
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2023
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths10%
Water Supply65%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains50%
Landscaping & Tree Planting25%
Street Lighting45%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water40%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space40%
Open Parkingnot started
Building & registration
- RERA registered
- Apr 2019
- Floors
- 13
Buyer community
Connect with other buyers and owners of Jasmine D, E and F โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Jasmine D, E and F. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.