PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

TRIMURTY HEIGHTS

by TRIMURTY INFRATECH

SURVEY NO 33 HISSA NO 6 PART PLOT NO 13 CTS NO 8974, AMBERNATH, 421501

Mar 2022
Possession
45.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 45.5%.

Official RERA facts

Registration
P51700021246
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
45.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting50%
Water conservation /Rain water harvestingdone
Energy managemcntdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jun 2019
Floors
17

Buyer community

Connect with other buyers and owners of TRIMURTY HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TRIMURTY HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.