KRISHNA SUDAMA RESIDENCY

by SAI HOMES

S.NO.7A, H.NO.1/3,1/4, KULGAON, 421503

Sept 2026
Possession
90.9%
Built
0
Complaints
175
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Sept 2024, now proposed Sept 2026 per the RERA filing.

Official RERA facts

Registration
P51700021284
Status
New
Stage
Certificate Signed
Possession
September 2026originally September 2024
Construction
90.9% complete
Units sold
91 of 175

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Jun 2019
Floors
9
Unit mix
175 res ยท 0 comm
Architect
MRS ARTI JAMGAONKAR

Buyer community

Connect with other buyers and owners of KRISHNA SUDAMA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KRISHNA SUDAMA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.