Under construction

SBM SKY

by SBM DEVELOPERS PVT LTD

S No 187 (PT) and 209 (PT), Thane, 400606

High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51700021785
Status
New
Stage
Certificate Signed
Possession
December 2027originally July 2025
Construction
51.1% complete
Units sold
125 of 225

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2019
Floors
30
Unit mix
225 res ยท 0 comm
Architect
DESIGN CONSORTIUM

Buyer community

Connect with other buyers and owners of SBM SKY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SBM SKY. Real notes from real buyers beat any brochure.

Start a discussion