Under construction

YASHVI RESIDENCY

by PATEL & CO.

CTS NO.1163,1164,1165, 1173 TO 1177, SHAHAD, 421103

Jun 2024
Possession
67.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Jun 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 67.3%.

Official RERA facts

Registration
P51700021794
Status
New
Stage
Certificate Signed
Possession
June 2024originally December 2022
Construction
67.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting10%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2019
Floors
9

Buyer community

Connect with other buyers and owners of YASHVI RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching YASHVI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.