BUILDING NO 5 VARDHAMAN VATIKA PAHSE II
278,280,275, OPPSITE JINADAL RECRTION, 421601
Dec 2027
Possession
81.8%
Built
1
Complaints
175
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700022222
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2023
- Construction
- 81.8% complete
- Units sold
- 102 of 175
RERA complaint record1 record
- ComplaintCC1260322629 May 2026RAMESH GOVIND MATE vs VARDHAMAN INFRASTRUCTURE
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths95%
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Planting95%
Water conservation /Rain water harvesting95%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Sept 2019
- Floors
- 89
- Unit mix
- 175 res ยท 0 comm
- Architect
- CHIRAG MISTRY
Buyer community
Connect with other buyers and owners of BUILDING NO 5 VARDHAMAN VATIKA PAHSE II โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching BUILDING NO 5 VARDHAMAN VATIKA PAHSE II. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.