Under construction

Harmony

by Trimity Constructions

TIKA NO 22, CTS NO 5/2 AND 5/3, Vishnu Nagar, 400602

Dec 2026
Possession
60.5%
Built
7
Complaints
48
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2023, now proposed Dec 2026 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700022306
Status
New
Stage
Certificate Signed
Possession
December 2026originally March 2023
Construction
60.5% complete
Units sold
23 of 48

RERA complaint record7 records

  • ComplaintCC1250262430 Jul 2025
    Snehal Pravin Joshi vs Trimity Constructions
    15 withdrawal order-CC12502624.pdf on MahaRERA
  • ComplaintCC1250257727 Jul 2025
    SNEHAL PRAVIN JOSHI vs Trimity Constructions
    14 withdrawal order-CC12502577.pdf on MahaRERA
  • ComplaintCC00600000059135429 Jul 2024
    Panchiben Boricha vs M/s Trimity Constructions
  • ComplaintCC00600000059135529 Jul 2024
    Chetan Boricha vs M/s Trimity Constructions
  • ComplaintCC00600000059135629 Jul 2024
    Rasila Boricha vs M/s Trimity Constructions
  • ComplaintCC00600000059135329 Jul 2024
    Nenshi Boricha vs M/s Trimity Constructions
  • ComplaintCC0060000001981541 Sept 2021
    Krupasagar Padmakar Patwardhan vs M/s Trimity Constructions
    CC006000000198154 Order.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
14
Unit mix
48 res ยท 0 comm
Architect
10 Folds Architects and Consultants

Buyer community

Connect with other buyers and owners of Harmony โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Harmony. Real notes from real buyers beat any brochure.

Start a discussion