Under construction
MARATHON NEXWORLD AURA-3
by MATRIX ENCLAVES PROJECTS DEV. PVT. LTD
22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/1, 30/1, 30/2, 80, Betawade Gaon, 400612
Dec 2026
Possession
16.3%
Built
2
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 16.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700022847
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 16.3% complete
- Units sold
- 0 of 0
RERA complaint record2 records
- ComplaintCC126042306 Jul 2026MATRIX ENCLAVES PROJECTS DEV. PVT. LTD vs Tushar Harischandra Pokhare
- ComplaintCC1250127316 Apr 2025Ketan Eknath Sawant vs MATRIX ENCLAVES PROJECTS DEV. PVT. LTDOrder of Ketan Sawant vs Matrix.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths20%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains30%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Oct 2019
- Floors
- 7
Buyer community
Connect with other buyers and owners of MARATHON NEXWORLD AURA-3 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MARATHON NEXWORLD AURA-3. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.