Under construction

SHRI SHIVANAND CHS

by Trimity Constructions

TIKKA NUMBER 20, CTS 25A, 25B, 26A, 26B, BHASKAR COLONY, 400602

Aug 2024
Possession
81.4%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jun 2023, now proposed Aug 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 81.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2024 per the RERA filing.

Official RERA facts

Registration
P51700024183
Status
New
Stage
Certificate Signed
Possession
August 2024originally June 2023
Construction
81.4% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply98%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station95%
Stack Parkingdone
Fitness Centerrdone

Building & registration

RERA registered
Jan 2020
Floors
9

Buyer community

Connect with other buyers and owners of SHRI SHIVANAND CHS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRI SHIVANAND CHS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.