Under construction

SKY CITY

by SUNRISE REALTORS

121/2, 121/3, 162/1, 120/4 PART, 120/8, 134/9/3 PART, Bhiwandi, 421305

Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2026, now proposed Jun 2028 per the RERA filing.

Official RERA facts

Registration
P51700024337
Status
New
Stage
Certificate Signed
Possession
June 2028originally December 2026
Construction
31.6% complete
Units sold
94 of 261

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2020
Floors
20
Unit mix
261 res ยท 0 comm
Architect
WASIQ NISAR AHMED NAKHUDA

Buyer community

Connect with other buyers and owners of SKY CITY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SKY CITY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.