GAMI ASTERS A WING

by THALIA AND GAMI ENTERPRISES

17 AND 18, Thane, 400701

High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700025311
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
98.6% complete
Units sold
129 of 143

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal75%
Water conservation /Rain water harvesting75%
Energy managemcntnot started
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2020
Floors
29
Unit mix
122 res ยท 21 comm
Architect
TRIARCH DESIGN STUDIO

Buyer community

Connect with other buyers and owners of GAMI ASTERS A WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GAMI ASTERS A WING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.