Under construction

SAI VAIBHAV PARADISE

by SHREE SAI DEVELOPERS

OLD SURVEY NO. 165, NEW SURVEY NO. 26 HISSA NO.3, SHRIDHAR MHATRE CHOWK, 421202

Jun 2022
Possession
39.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 39.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.

Official RERA facts

Registration
P51700025525
Status
New
Stage
Certificate Signed
Possession
June 2022
Construction
39.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jun 2020
Floors
12

Buyer community

Connect with other buyers and owners of SAI VAIBHAV PARADISE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI VAIBHAV PARADISE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.