PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SUDAM RESIDENCYMahaRERA P51700025768

by SAIKRUPA DEVELOPERS

SURVEY NO. 90, HISSA NO. 9/D, MAUJE GAONDEVI, 421202

Sept 2027
Possession
100%
Built
0
Complaints
44
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Sept 2027 per the RERA filing.

Official RERA facts

Registration
P51700025768
Status
New
Stage
Certificate Signed
Possession
September 2027originally June 2024
Construction
100% complete
Units sold
29 of 44

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

BARKABAI SUDAM MHATRE & OTHERS

Possession extension history

  • EXT51700024197Revised to June 2025

    Due to the pandemic situation prevailing for almost last 2 years construction activity also affected adversely. However we have completed the construction of building but procedure to get Occupancy Certificate is under Process. Copy of Building photo is enclosed herewith for your reference.

  • EA01072501906Revised to June 2026

    We have completed the construction of building but procedure to get Occupancy Certificate is under Process. Copy of Building photo is enclosed herewith for your reference.

  • EA29062621587Revised to September 2027

    We had completed the project but during the time of getting different NOCโ€™s for Occupancy Certificate there is some revised work guided from Fire NOC Department & Rain Harvesting Department. We are making all possible efforts to complete the balance work at the earliest and is committed towards completing the project responsibly.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Jul 2020
Floors
11
Unit mix
44 res ยท 0 comm
Architect
GOPINATH GANDHE
Plot / CTS / survey no.
SURVEY NO. 90, HISSA NO. 9/D
Planning authority
KALYAN DOMBIVLI MUNICIPAL CORPORATION
Approved layout land
1,300 sq.m
Land for this registration
1,300 sq.m
Permissible built-up area
1,964.35 sq.m
Registered office
SUDAM RESIDENCY
Plot boundaries
North
SURVEY NO 75
South
SURVEY NO 69
East
SURVEY NO 74
West
SURVEY NO 72
Parking
14 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 49328
    IFSC HDFC0000947
    SHOP NO 15-17, SONAL BUSINESS PARK, NEAR GHARDA CIRCLE, MIDC, DOMBIVLI EAST, 421203

Commencement Certificate documents

  • CC.pdf
  • Revised CC.pdf

Buyer community

Connect with other buyers and owners of SUDAM RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SUDAM RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.