PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AASHRAY AANAND PHASE-II

by DREAM CORPRATION

S.NO-140/2A,141/1B AND 141/1/E/5/B/1, GAIKWADPADA, 421501

Nov 2022
Possession
86.4%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Nov 2022) has passed with construction at 86.4%.

Official RERA facts

Registration
P51700026268
Status
New
Stage
Certificate Signed
Possession
November 2022
Construction
86.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvesting50%

Building & registration

RERA registered
Sept 2020
Floors
6

Buyer community

Connect with other buyers and owners of AASHRAY AANAND PHASE-II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AASHRAY AANAND PHASE-II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.