Under construction
MOHAN DEEP
OLD SURVEY NO 2 HISSA NO 6 PT NEW SURVEY NO 23 HISSA NO 6 PART, MHARAL, 421301
Sept 2026
Possession
87.6%
Built
0
Complaints
70
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700026561
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026
- Construction
- 87.6% complete
- Units sold
- 10 of 70
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths86%
Water Supply67%
Sewerage (Chamber, Lines, Septic Tank , STP)82%
Landscaping & Tree Plantingnot started
Street Lighting27%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements48%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started
Open Parking50%
Building & registration
- RERA registered
- Oct 2020
- Floors
- 20
- Unit mix
- 70 res ยท 0 comm
- Architect
- GEO ASSOCIATES
Buyer community
Connect with other buyers and owners of MOHAN DEEP โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MOHAN DEEP. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.