SUKUR SAPPHIRE PHASE I

by RAJARAM CONSTRUCTION

SNO10 HNO3A3B SNO7 HNO17, Thane, 400610

Caution
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 86.4%.

Official RERA facts

Registration
P51700027081
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
86.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting60%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Nov 2020
Floors
21

Buyer community

Connect with other buyers and owners of SUKUR SAPPHIRE PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SUKUR SAPPHIRE PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.