Under construction

NEXUS PARK

by NEXUS GROUP

SURVEY NO 6 HISSA NO 7/A, Village Dawale, 400612

Jun 2027
Possession
73%
Built
0
Complaints
274
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700027450
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2026
Construction
73% complete
Units sold
144 of 274

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)15%
Storm Water Drains15%
Treatment And Disposal Of Sewage And Sullage Water75%
Solid Waste Management And Disposal15%
Water conservation /Rain water harvesting15%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station15%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2020
Floors
27
Unit mix
261 res ยท 13 comm

Buyer community

Connect with other buyers and owners of NEXUS PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.