PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GURUNATH GALAXY

by MUKTA DEVELOPERS

SURVEY NO.12 HISSA NO.7, AT MOUJE, 421605

Sept 2027
Possession
23.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Sept 2023, now proposed Sept 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Official RERA facts

Registration
P51700028392
Status
New
Stage
Certificate Signed
Possession
September 2027originally September 2023
Construction
23.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2021
Floors
8

Buyer community

Connect with other buyers and owners of GURUNATH GALAXY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GURUNATH GALAXY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.