Dec 2026
Possession
70.5%
Built
1
Complaints
40
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700028707
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2023
- Construction
- 70.5% complete
- Units sold
- 16 of 40
RERA complaint record1 record
- ComplaintCC1250129218 Apr 2025Shams Tabrez Asghar Ali Ansari vs S V BUILDERSOrder of Shams Ansari.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Building & registration
- RERA registered
- Mar 2021
- Floors
- 5
- Unit mix
- 40 res ยท 0 comm
- Architect
- NAKHUDA ASSOCIATES
Buyer community
Connect with other buyers and owners of AL AMIN TOWER โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AL AMIN TOWER. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.